Construction of 26-inch Oil Pipeline 132/11 kV Substations
Two 132/11 kV substations for the 26-inch pump stations, plus extension of a 63/6.3 kV substation at Bandar pump station.

A selection of substation projects delivered from 6.3 kV up to 400 kV, covering greenfield construction, capacity extension and feeder additions.

Two 132/11 kV substations for the 26-inch pump stations, plus extension of a 63/6.3 kV substation at Bandar pump station.

Construction of six 132/11 kV substations for the Persian Gulf water pump stations as a PC project.

Increasing the capacity of the Amin 400/230/63/20 kV substation, executed as a PC project.

Construction of the substation with extension of two 63 kV line feeders and one 230 kV transformer feeder, plus the connected 63 kV transmission line.

63/20 kV substation and connected 63 kV transmission line for the electrification of the industrial zone and 200 pharmaceutical high-tech subsidiaries.

Construction and development of the 230/20 kV substation including two 230 kV transformer feeders, executed as an EPC project.

230/63 kV and 63/11 kV substations supplying pump station No. 5 on the crude-oil transfer pipeline.

132/6.9 kV pelletizing plant substation with extension of two 132 kV line feeders, executed as EPC.

Two 63 kV capacitor banks and two 63 kV line feeders in the North Ray 63/20 kV substation, with extension of the related 230/63/20 kV substation.

Construction of the Mana Energy 63/20 kV substation together with substation extension works.

A full one-and-a-half breaker diameter at 230 kV, completion of two existing incomplete diameters and connection of the second 230 kV line feeder.

132/20 kV substation for the Babak copper mine together with approximately 40 km of related 132 kV overhead line.